Finders Resourced has announced the following Board appointments effective immediately: Colin Moorhead to join as Non-Executive Chairman; Roderick Webster ...
Owing to a premature bearing failure to the jaw crusher the crushing of fresh ore at FindersResources' Wetar Copper Project in Indonesia has been restricted. The failure has caused the supply of leached ...
FindersResources has described results received from pre-development activities at the Lerokis deposit of the Wetar Copper Project in Indonesia as outstanding. The high-grade results are from the final ...
PRODUCTION at FindersResources’ Wetar Copper Project has been impacted by an interruption to the 25,000 tonnes/annum copper cathode SX-EW plant. An overflow of organic and aqueous solution into the electrowinning ...
FindersResources has received a letter from Eastern Field Developments Ltd stating its intention to make an off-market takeover offer for all of the shares in Finders. Eastern Field is a consortium comprising ...
FindersResources achieved record production of copper cathode during the June quarter at its Wetar Copper Project on Wetar Island in Indonesia. There were 6804 tonnes of copper stripped, up from 6125 ...
THE Wetar Copper Project on Wetar Island in eastern Indonesia continues to perform strongly for FindersResources. During May, the SX-EW plant exceeded the company’s annual production target of 28,000 ...
RECENT results from the Lerokis deposit of FindersResources’ Wetar Copper Project signify potential to expand existing resources. Lerokis will be the second open pit mine at the project following completion ...
WITH the Wetar Copper Project expected to reach full production capacity by the end of 2016, FindersResources plans to continue exploring at and near-mine targets in a bid to identify further copper. ...
Geotechnical and metallurgical diamond drilling at the Lerokis deposit within FindersResources Wetar Copper Project in Indonesia has intersected high grade copper mineralisation. These results signify ...
... transaction is expected to close during the second calendar quarter of 2017. A finders' fee of $100,000 is to be paid to an arm’s length company in association with the transaction.
In light of the sale, ...
FindersResources intends to use A$12 million raised in a placement to advance its operating Wetar Copper Project in Indonesia. Plans include drilling out the existing resources at Lerokis deposit and ...
The ramp-up of the new copper cathode SX-EW plant at FindersResources Wetar Copper Project in Indonesia continues with the plant having reached annual nameplate capacity of 25,000 tonnes on a number of ...
Ramp up of the recently commissioned 25,000 tonne/annum copper cathode solvent extraction-electrowinning (SX-EW) plant at FindersResources Wetar Copper Project in Maluku Barat Daya, Indonesia, has reached ...
More than 300 tonnes of LME Grade A copper cathode has been stripped from the recently commissioned 25,000 tonnes per annum copper cathode solvent extraction electrowinning (SX-EW) plant at FindersResources ...
First copper has been plated at FindersResources’ recently commissioned 25,000 tonne/annum copper cathode solvent extraction electrowinning (SX-EW) plant at the Wetar Copper Project in Indonesia.
Commissioning ...
FindersResources announces that Chris Farmer has resigned as a director and has stepped down from all executive and board roles within the Finders Group.
Gulf Manganese has completed its search ...
THE Wetar Copper Project expansion on Wetar Island remains on track for commissioning and first production during the current quarter. FindersResources says the expansion project will increase annual ...
The copper cathode SX-EW expansion project at FindersResources’ Wetar Copper Project on Wetar Island in eastern Indonesia is progressing well. The expansion project will have annual capacity of 25,000 ...