Owing to a premature bearing failure to the jaw crusher the crushing of fresh ore at Finders Resources' Wetar Copper Project in Indonesia has been restricted. The failure has caused the supply of leached ...
Finders Resources has described results received from pre-development activities at the Lerokis deposit of the Wetar Copper Project in Indonesia as outstanding. The high-grade results are from the final ...
PRODUCTION at Finders Resources’ Wetar Copper Project has been impacted by an interruption to the 25,000 tonnes/annum copper cathode SX-EW plant. An overflow of organic and aqueous solution into the electrowinning ...
... the Wetar Copper Project in Indonesia at almost A$178 million. The consortium announced its intention to price the offer at A$0.23 per share, which represents a 9% premium to Finders’ three month volume ...
Finders Resources achieved record production of copper cathode during the June quarter at its Wetar Copper Project on Wetar Island in Indonesia. There were 6804 tonnes of copper stripped, up from 6125 ...
THE Wetar Copper Project on Wetar Island in eastern Indonesia continues to perform strongly for Finders Resources. During May, the SX-EW plant exceeded the company’s annual production target of 28,000 ...
RECENT results from the Lerokis deposit of Finders Resources’ Wetar Copper Project signify potential to expand existing resources. Lerokis will be the second open pit mine at the project following completion ...
WITH the Wetar Copper Project expected to reach full production capacity by the end of 2016, Finders Resources plans to continue exploring at and near-mine targets in a bid to identify further copper. ...
Geotechnical and metallurgical diamond drilling at the Lerokis deposit within Finders Resources Wetar Copper Project in Indonesia has intersected high grade copper mineralisation. These results signify ...
Finders Resources intends to use A$12 million raised in a placement to advance its operating Wetar Copper Project in Indonesia. Plans include drilling out the existing resources at Lerokis deposit and ...
...
The various government ministries have accepted that mining products pay a royalty on contained metal, whereas smelters pay VAT on production. This is not quite so easy for the Wetar project of PT Batutua ...
The ramp-up of the new copper cathode SX-EW plant at Finders Resources Wetar Copper Project in Indonesia continues with the plant having reached annual nameplate capacity of 25,000 tonnes on a number of ...
Ramp up of the recently commissioned 25,000 tonne/annum copper cathode solvent extraction-electrowinning (SX-EW) plant at Finders Resources Wetar Copper Project in Maluku Barat Daya, Indonesia, has reached ...
... Wetar Copper Project in Indonesia.
The rate of copper cathode stripping continues to increase as production levels from the SX-EW plant ramp up.
Concurrently, the existing 3000 tonnes/annum copper ...
First copper has been plated at Finders Resources’ recently commissioned 25,000 tonne/annum copper cathode solvent extraction electrowinning (SX-EW) plant at the Wetar Copper Project in Indonesia.
Commissioning ...
THE Wetar Copper Project expansion on Wetar Island remains on track for commissioning and first production during the current quarter. Finders Resources says the expansion project will increase annual ...
The copper cathode SX-EW expansion project at Finders Resources’ Wetar Copper Project on Wetar Island in eastern Indonesia is progressing well. The expansion project will have annual capacity of 25,000 ...
Work continues on construction of the 25,000 tonnes/annum copper cathode SX-EW plant at Finders Resources’ Wetar Copper Project.
Mobilization of the second earthmoving fleet is proceeding with an expected ...
Emerging low-cost copper cathode producer Finders Resources has passed the final milestone in financing of the Wetar Copper Project on Wetar Island. Finders’ Indonesian subsidiary PT Batutua Tembaga Raya ...