Altura Mining has announced the completion of the first stage of the commissioning for its 100 per cent owned flagship Altura Lithium Project.

TAMMay24 img03Altura’s commissioning team has completed wet commissioning of the crushing circuit and stockpiled, crushed ore is now available to feed into the processing plant.

The entire commissioning phase is scheduled for completion by the end of June 2018, at which time the operation will be ramped up towards full throughput capacity. The Company is working to a timetable which remains on track for first lithium concentrate production in Q2 2018 and first shipment in July 2018.

In conjunction with the commissioning activities that have been occurring over the past few months, site management have been assembling the plant operations and maintenance teams in line with the Owner Operator model that has been adopted.

“The commissioning milestone marks a significant step for the Altura team. We have to remember this was a greenfields site that required the procurement and installation of all site infrastructure. I am very confident of our team’s ability to commission a processing plant with both dense media separation and flotation circuits and transform us into a producer”, said Altura Managing Director Mr James Brown.